Vendor Governance Bee
NSOffice.AIStep 1 of 3 · What the design team sent
Quantities off the IFC drawings
IFC rev 2, issued 22 Dec 2025. As received, with nothing added and nothing corrected.
4 rows are incomplete. A missing quantity, unit or drawing. The Bee leaves each blank rather than guessing a measurement, and says below how each was settled. Show them
| Code | Description | Kind | Unit | Quantity | Drawing |
|---|---|---|---|---|---|
| DRW-031 | Fixing of main and internal door frames with grouting | Labour | nos | 1,176 | A-610 |
| DRW-032 | Hanging of door shutters and fixing of hardware | Labour | nos | 1,422 | A-610 |
| DRW-033 | Fire door installation with intumescent sealing | Labour | nos | 78 | A-610 |
| DRW-034 | Surface preparation of doors for polish and paint | Labour | nos | 1,422 | A-310 |
| DRW-035 | Fixing of uPVC windows, ventilators and fixed glazing | Labour | m2 | 12,440 | A-610 |
| DRW-036 | Glazing, beading and silicone sealing | Labour | m2 | 15,560 | A-610 |
| DRW-037 | Balcony sliding door fixing and track alignment | Labour | m2 | 3,120 | A-610 |
| DRW-038 | Fixing of safety grills and mosquito mesh | Labour | m2 | 6,920 | A-620 |
| ELE-049 | Concealed conduit laying in slabs, beams and walls | Labour | m | 1,09,200 | E-250 |
| ELE-050 | Riser conduit, cable tray and bus duct support erection | Labour | m | 16,180 | E-250 |
| ELE-051 | Wiring, looping and termination in conduit | Labour | m | 2,74,600 | E-250 |
| ELE-052 | Low voltage wiring, data, telephone and television | Labour | m | 69,600 | E-250 |
| ELE-053 | Fixing of switches, sockets, plates and fan points | Labour | m | 19,580 | E-250 |
| ELE-054 | Earthing pit excavation, strip laying and continuity testing | Labour | m | 2,200 | E-250 |
| ELE-056 | Testing, load trial and MSEDCL liaison | Labour | nos | 1 | E-250 |
| ELV-003 | Lift installation, testing and commissioning | Labour | nos | 5 | E-601 |
| ELV-004 | Lift pit waterproofing and machine room civil works | Labour | lot | 1 | A-501 |
| EXT-020 | Earthwork, grading and compaction, external areas | Labour | m2 | 9,800 | C-301 |
| EXT-021 | Sub base laying, kerb fixing and paver laying | Labour | m2 | 9,240 | C-301 |
| EXT-022 | Bituminous road laying and rolling | Labour | m2 | 3,200 | C-301 |
| EXT-023 | Compound wall erection and gate installation | Labour | m2 | 1,240 | C-310 |
| EXT-024 | Storm water drain, manhole and external sewer laying | Labour | m2 | 3,324 | C-330 |
| EXT-025 | Street lighting erection, cabling and testing | Labour | m2 | 1,848 | C-320 |
| EXT-026 | Lawn preparation, turfing and tree planting | Labour | m2 | 5,200 | C-340 |
| EXT-027 | Irrigation system laying, testing and commissioning | Labour | m2 | 3,400 | C-340 |
| EXT-028 | Play area surfacing and equipment installation | Labour | m2 | 480 | C-320 |
| FAC-025 | Survey, setting out and bracket fixing on slab edges | Labour | m2 | 9,800 | A-401 |
| FAC-026 | Installation of mullions and transoms | Labour | m2 | 9,800 | A-401 |
| FAC-027 | Glass installation, structural glazing and DGU | Labour | m2 | 11,400 | A-401 |
| FAC-028 | Structural and weather sealant application | Labour | m2 | 11,400 | A-401 |
| FAC-029 | Water leakage testing, cleaning and handover | Labour | m2 | 11,400 | A-401 |
| FAC-030 | ACP panel fabrication and installation | Labour | m2 | 2,400 | A-401 |
| FAC-031 | Dry stone cladding fixing, podium | Labour | m2 | 1,240 | A-406 |
| FAC-032 | Glass railing and handrail installation | Labour | m2 | 2,180 | A-406 |
| FIR-027 | Hydrant and sprinkler installation, hydro testing and fire NOC support | Labour | lot | 1 | F-130 |
| FLR-031 | Laying of vitrified and ceramic floor tiles with adhesive | Labour | m2 | 1,35,400 | A-330 |
| FLR-032 | Laying of wall tiles and dado with adhesive | Labour | m2 | 45,800 | A-320 |
| FLR-033 | Skirting, grouting, cleaning and protection | Labour | m2 | 4,800 | A-330 |
| FLR-034 | Screed laying and floor levelling | Labour | m2 | 9,400 | A-330 |
| FLR-035 | Laying of granite and marble in floors and cladding | Labour | m2 | 12,480 | A-331 |
| FLR-036 | Laying of Kota stone in service areas and basements | Labour | m2 | 11,040 | A-330 |
| FLR-037 | Edge polishing, nosing and mirror polishing | Labour | m2 | 4,580 | A-330 |
| FLR-038 | Kitchen platform fabrication, cut outs and fixing | Labour | m2 | 3,400 | A-330 |
| MAS-002 | Internal plaster, 12 mm | Labour | m2 | missing | missing |
| MAS-009 | Block work in superstructure, 200 mm | Labour | m2 | 54,200 | A-301 |
| MAS-010 | Block work in superstructure, 150 and 100 mm | Labour | m2 | 19,400 | A-301 |
| MAS-011 | External plaster, 20 mm, two coats | Labour | m2 | 62,800 | A-311 |
| MAS-012 | Ceiling plaster, 6 mm | Labour | m2 | 42,600 | A-310 |
| MAS-013 | Chicken mesh at RCC junctions and groove cutting at service chases | Labour | m2 | 18,600 | A-310 |
| PLB-043 | Laying of CPVC and uPVC pipes with sleeves and clamps | Labour | m | 64,900 | P-101 |
| PLB-044 | Riser and shaft piping erection with supports | Labour | m | 11,740 | P-101 |
| PLB-045 | Fixing of sanitaryware, CP fittings and accessories | Labour | m | 6,132 | P-120 |
| PLB-046 | Pump room erection, header fabrication and alignment | Labour | m | 2,460 | P-130 |
| PLB-047 | Pressure testing, flushing and chlorination | Labour | m | 24,700 | P-130 |
| PLB-048 | STP and rainwater harvesting erection and trial run | Labour | m | 6 | P-150 |
| PNT-011 | Putty application and sanding, internal walls | Labour | m2 | 1,98,400 | A-310 |
| PNT-012 | Primer coat, internal walls | Labour | m2 | 1,98,400 | A-310 |
| PNT-013 | Two coats acrylic emulsion, internal walls | Labour | m2 | 1,98,400 | A-310 |
| PNT-014 | Putty, primer and emulsion, internal ceilings | Labour | m2 | 42,600 | A-310 |
| PNT-015 | Surface preparation and crack filling, external | Labour | m2 | 62,800 | A-311 |
| PNT-016 | Alkali resistant primer, external walls | Labour | m2 | 62,800 | A-311 |
| PNT-017 | Two coats textured exterior emulsion | Labour | m2 | 62,800 | A-311 |
| PNT-018 | Anti-carbonation coating on exposed RCC | Labour | m2 | 7,400 | A-311 |
| PNT-019 | Enamel painting of MS grills and railings | Labour | m2 | 6,240 | A-311 |
| PNT-020 | Melamine polishing of doors and frames | Labour | m2 | 3,180 | A-310 |
| PNT-021 | Epoxy coating, basement floors and plant rooms | Labour | m2 | 11,400 | A-330 |
| PNT-022 | Line marking and signage painting, basements | Labour | m2 | 8,600 | A-330 |
| PNT-023 | Scaffolding, staging and protection for painting | Labour | m2 | 62,800 | A-311 |
| STR-004 | RCC work including shuttering and deshuttering | Labour | sq ft | 2,64,000 | S-001 |
| STR-005 | Excavation and shoring, 2 basements | Labour | m3 | 18,400 | C-010 |
| WPF-001 | Basement raft and retaining wall membrane, APP modified | Labour | m2 | 21,400 | C-020 |
| WPF-002 | Podium deck membrane with protection screed | Labour | m2 | 8,600 | A-120 |
| WPF-003 | Lift pit and sump waterproofing, crystalline | Labour | m2 | 1,240 | A-501 |
| WPF-004 | Toilets, balconies and utility areas, polyurethane coating | Labour | m2 | 24,800 | A-320 |
| WPF-005 | Terrace and overhead tank waterproofing | Labour | m2 | 6,400 | A-130 |
What happens when you generate the BOQ
- 318rows received
243 material, 75 labour, measured off 48 drawings.
- groupedby spec key
Rows sharing one are a single purchasable item. Material and labour never merge.
- PO or WOtagged
Material is bought on a purchase order, labour on a work order.
- 4left blank
A quantity is a measurement. Gaps go to a person, never to a guess.
Grouping and adding, nothing else. You can change any line afterwards, until you freeze it.