The drawings these quantities came off

38 drawings

Of the 48 sheets in IFC rev 2, these are the ones something was measured on. Pick one to see what came off it.

C-330 Storm water and external drainageRev 2 · issued 22 Dec 2025 · scale 1:200
C-330Structure1:200The drawing PDFs are not part of this collateral, so this is a placeholder.
What was measured on this drawing
X-01Supply of pavers, kerbs, road materials, wall and drainage units19,408 m2
X-02Supply of external lighting, services, turf, plants and play equipment12,862 m2
X-03Roads, paving, compound wall and drainage, labour only26,804 m2
See these in the BOQ