See the BOQ
Step 1 of 3 · What the design team sent

Quantities off the IFC drawings

IFC rev 2, issued 22 Dec 2025. As received, with nothing added and nothing corrected.

4 rows are incomplete. A missing quantity, unit or drawing. The Bee leaves each blank rather than guessing a measurement, and says below how each was settled. Show them
CodeDescriptionKindUnitQuantityDrawing
ELE-048Spare conduit and draw wire for smart home provisionMaterialmissing8,600E-201
EXT-016Ornamental trees and shrubs, nursery grownMaterialm20C-340
FAC-005Mock up panel for approvalMaterialm224missing
MAS-002Internal plaster, 12 mmLabourm2missingmissing
Showing 4 of 318 rows.
What happens when you generate the BOQ
  1. 318rows received

    243 material, 75 labour, measured off 48 drawings.

  2. groupedby spec key

    Rows sharing one are a single purchasable item. Material and labour never merge.

  3. PO or WOtagged

    Material is bought on a purchase order, labour on a work order.

  4. 4left blank

    A quantity is a measurement. Gaps go to a person, never to a guess.

Grouping and adding, nothing else. You can change any line afterwards, until you freeze it.