Finished · N.S. Construction Pvt Ltd
Sylvan Crest, Wakad
G+18 residential tower with one basement. 2,31,000 sq ft, 124 apartments. Started 18 Mar 2025, handed over 28 Nov 2025.
₹139.80 CrBudget
₹142.40 CrFinal cost
+1.9%Against budget
11Vendors used
How it went
Finished 1.9 percent over budget and three weeks late. Steel and RCC ran clean; the facade vendor slipped twice and was paid under protest.
18 Mar 2025BudgetQuantities received284 rows off IFC rev 1. Two had no quantity.
29 Mar 2025BudgetBOQ frozen42 lines in 12 sections.
2 Apr 2025BudgetBudget set at Rs 139.8 CrPriced off Hillview and Lakeside.
20 Apr 2025PO and WOAll 12 RFIs out38 proposals came back.
11 Jun 2025PO and WOLast order issuedRs 141.1 Cr awarded, 0.9 percent over budget.
4 Aug 2025GovernanceFacade vendor 19 days lateRecovery plan asked for. Second slip in six weeks.
22 Sept 2025GovernanceRs 11.4 L held backFacade billed ahead of measured work. Paid under protest at handover.
28 Nov 2025ClosedHanded overRs 142.4 Cr final. Three weeks late.