Finished · N.S. Construction Pvt Ltd
Riverside One, Kharadi
G+22 residential tower with two basements. 2,88,000 sq ft, 156 apartments. Started 9 Jul 2024, handed over 14 Jun 2025.
₹174.20 CrBudget
₹171.80 CrFinal cost
−1.4%Against budget
12Vendors used
How it went
Finished 1.4 percent under budget and on time. The best run of the three. Lifts arrived early and the plumbing package never moved.
9 Jul 2024BudgetQuantities received331 rows off IFC rev 2. All complete.
19 Jul 2024BudgetBOQ frozen48 lines in 12 sections.
24 Jul 2024BudgetBudget set at Rs 174.2 CrPriced off Hillview, Lakeside and Maple Court.
16 Aug 2024PO and WOAll 12 RFIs out44 proposals came back.
2 Oct 2024PO and WOLast order issuedRs 171.8 Cr awarded, 1.4 percent under budget.
15 Jan 2025GovernanceLifts arrived three weeks earlyRail fixing started ahead of the slab.
30 Apr 2025GovernanceNothing held back all jobNo vendor billed above its order rate.
14 Jun 2025ClosedHanded overRs 171.8 Cr final. On the planned date.