Finished · N.S. Construction Pvt Ltd
Orchid Park, Hinjewadi
G+14 residential tower with one basement. 1,96,000 sq ft, 98 apartments. Started 26 Feb 2024, handed over 7 Feb 2025.
₹110.40 CrBudget
₹108.60 CrFinal cost
−1.6%Against budget
9Vendors used
How it went
Finished 1.6 percent under budget and eleven days late. The painting package was awarded late and never caught up.
26 Feb 2024BudgetQuantities received247 rows off IFC rev 2. One had no unit.
8 Mar 2024BudgetBOQ frozen38 lines in 11 sections.
12 Mar 2024BudgetBudget set at Rs 110.4 CrPriced off Hillview and Maple Court.
2 Apr 2024PO and WO11 RFIs out29 proposals came back.
28 Jun 2024PO and WOPainting awarded eleven weeks lateOnly two vendors quoted. The RFI went out twice.
19 Nov 2024GovernancePainting 24 days behindStarted late and never caught up.
8 Jan 2025GovernanceRs 4.2 L held backPainting billed for floors it had not finished.
7 Feb 2025ClosedHanded overRs 108.6 Cr final. Eleven days late.