NSOffice.AIStep 2 of 3 · BOQ
46 line items in 12 sections
Grouped the way site and procurement buy. Open a section to add, change or remove a line, then freeze it.
Masonry and plaster4 items · 2 PO, 2 WO1 line needs attentionnot priced yet
| Item | Type | Description | Unit | Qty | Take-off rows | Actions |
|---|---|---|---|---|---|---|
| M-01 | PO | Supply of AAC blocks, 100 to 200 mm | m3 | 9,390 | MAS-001, 003, 004 | |
| M-03 | PO | Supply of block jointing mortar and ready-mix plaster | MT | 7,286 | MAS-005, 006, 007, 008 |
How this BOQ was made
- 318take-off rows
What the design team measured off the issued drawings.
- 46line items
Rows sharing a spec key became one item. Their quantities were added.
- 25 PO, 21 WOtagged
Material is bought on a purchase order, labour on a work order.
- 4needed attention
A quantity is a measurement, so each one waits for a person. Each line says what is missing.
Grouping and adding, nothing else. The same input gives the same BOQ every time.