46 line items in 12 sections
Grouped the way site and procurement buy. Open a section to add, change or remove a line, then freeze it.
Facade4 items · 2 PO, 2 WO1 line needs attentionnot priced yet
| Item | Type | Description | Unit | Qty | Take-off rows | Actions |
|---|---|---|---|---|---|---|
| G-03 | WO | Facade glazing installation and sealing, labour only | m2 | 53,800 | FAC-025, 026, 027, 028, 029 | |
| G-04 | WO | ACP, stone cladding and railing installation, labour only | m2 | 5,820 | FAC-030, 031, 032 |
How this BOQ was made
- 318take-off rows
What the design team measured off the issued drawings.
- 46line items
Rows sharing a spec key became one item. Their quantities were added.
- 25 PO, 21 WOtagged
Material is bought on a purchase order, labour on a work order.
- 4needed attention
A quantity is a measurement, so each one waits for a person. Each line says what is missing.
Grouping and adding, nothing else. The same input gives the same BOQ every time.