46 line items in 12 sections
Grouped the way site and procurement buy. Open a section to add, change or remove a line, then freeze it.
Doors and windows5 items · 3 PO, 2 WOnot priced yet
| Item | Type | Description | Unit | Qty | Take-off rows | Actions |
|---|---|---|---|---|---|---|
| D-04 | WO | Door installation and preparation, labour only | nos | 4,098 | DRW-031, 032, 033, 034 | |
| D-05 | WO | Window and glazing installation, labour only | m2 | 38,040 | DRW-035, 036, 037, 038 |
How this BOQ was made
- 318take-off rows
What the design team measured off the issued drawings.
- 46line items
Rows sharing a spec key became one item. Their quantities were added.
- 25 PO, 21 WOtagged
Material is bought on a purchase order, labour on a work order.
- 4needed attention
A quantity is a measurement, so each one waits for a person. Each line says what is missing.
Grouping and adding, nothing else. The same input gives the same BOQ every time.